National Iranian Oil Company v Crescent Petroleum Company International Limited & Crescent Gas Corporation Limited
Where bifurcation has been ordered and liability determined, a party in an arbitration is precluded on grounds of res judicata and/or abuse of process from referring to and relying on matters in support of its separate defence to quantum if those matters could or should also have been raised in relation to liability. A Tribunal must be obviously wrong about this issue before there are grounds for an aggrieved party to seek an appeal on a question of law to the English courts.
Partners Jonathan Choo and Shaun Lee, and associate Gladys Yeo from the Singapore dispute resolution group at Bird & Bird ATMD explain the implications of the decision.
First, the decision emphasises that a defendant would be precluded from raising any defences at the remedies stage which could or should be raised at the liability stage in the situation where bifurcation has been ordered and liability has been determined. This suggests that a defendant should be mindful to raise all available defences at the appropriate juncture of the arbitral proceedings or otherwise be precluded from challenging the award on that basis in subsequent setting aside or enforcement proceedings before the English courts.
In this regard, a bifurcated hearing (whether in arbitration or in court) does not allow a party to advance cases which would place a Tribunal in an ‘unreal’ position or a position which the tribunal could not have taken if there had been a single hearing. Specifically, the Court considered that the test is not whether the applicant was seeking to run ‘inconsistent’ cases at different stages of the hearing, but whether it would place the tribunal or court hearing the matter in an invidious position. This is perhaps somewhat akin to the position where a party may plead alternative causes of action but not inconsistent versions of fact or inconsistent pleadings which offend common sense.
Second, the English court recognised that an applicant seeking an appeal against an arbitral award must satisfy the Court that ‘the Tribunal’s decision was obviously wrong’ and not merely ‘anything wrong’ when applying a legal test in the arbitration. The mere fact that the tribunal does not refer to the case law or spell out the test which they were intending to apply, does not amount to a justiciable (and appealable) error of law. Finally, the English court has reiterated that a party’s waiver of the right to appeal an award on a question of law under Section 69 of the Act is a question of construction, and sufficiently clear wording, albeit not express reference to Section 69 of the Act, is necessary.
The applicant, National Iranian Oil Company (“NIOC”) agreed with Crescent Petroleum Company International Limited (“Crescent Petroleum”), to supply and sell to Crescent Petroleum specified quantities of natural gas for a period of 25 years (the “Agreement”). Crescent Petroleum had assigned its rights under the contract to Crescent Gas Corporation Limited (“Crescent Gas”) before the first delivery of gas was due. Crescent Petroleum and Crescent Gas (collectively, “Crescent”) commenced arbitration proceedings as NIOC had failed to deliver gas pursuant to the Agreement.
The Tribunal had ordered a bifurcation of the proceedings – (1) first, to determine all jurisdictional issues and all issues relevant to liability; and (2) second, to determine the remedies to be awarded if liability was established.
Having determined that it had jurisdiction over the claims brought by Crescent, and that NIOC had been and remained in breach of its obligation to deliver gas under the Agreement, the Tribunal proceeded to consider the remedies to be awarded.
NIOC argued that in assessing Crescent’s loss and hence the damages to be awarded, the Tribunal must take into account the fact that sanctions and various other events affecting NIOC’s ability to supply gas under the Agreement would have reduced the amount of gas which could have been supplied and/or received under the Agreement.
In response, Crescent argued that NIOC’s aforesaid argument was precluded by the doctrines of res judicata and abuse of process as they could and should have been advanced during the liability phase. NIOC had failed to do so. Crescent argued that NIOC’s raising of sanctions (and related) issues at the quantum stage was an attempt to circumvent the Tribunal’s findings on liability.
The Tribunal agreed with Crescent’s submissions on this issue and awarded damages to Crescent (the “Partial Award”).
NIOC then made the present application for permission to appeal against the Partial Award under section 69 of the Act on the following question of law:
“[W]here bifurcation has been ordered and liability determined, is a defendant/respondent precluded on grounds of res judicata and/or abuse of process from referring to and relying on matters in support of its separate defence to quantum merely because those matters might or could also have been raised in relation to liability?”
As a threshold issue, Crescent argued that parties had agreed to waive their right to appeal a point of law, and it was therefore not open to NIOC to appeal against the Partial Award under section 69 of the Act, on the basis that parties had incorporated Article 28.6 of the 1998 International Chamber of Commerce rules (the “ICC Rules 1998”) in their contractual agreement, which provides that:
“Every Award shall be binding on the parties. By submitting the dispute to arbitration under these Rules, the parties undertake to carry out any Award without delay and shall be deemed to have waived their right to any form of recourse insofar as such waiver can validly be made.”
The arbitration clause in the Agreement provided that any dispute, controversy or claim is to be finally settled by arbitration in accordance with the “Procedures for Arbitration” as contained in Annex 2 of the Agreement. In turn, paragraph 9 of Annex 2 provides that in the case of a gap in the procedural rules of arbitration, then ‘the procedural rules of arbitration of the International Chamber of Commerce (ICC) shall apply’.
Crescent argued that, since the arbitration clause in Article 22.2 and Annex 2 of the Agreement did not contain any rules about appeals to the court on points of law, there was a gap which is filled by Article 28.6 of the ICC Rules and the exclusion of the right to appeal on a point of law contained within that provision.
The Court highlighted that whether there was an agreement between the parties to waive their right to appeal a point of law is a question of construction. The Court cited with approval Shell Egypt West Manzala v Dana Gas [2009] EWHC 2097 (Comm), where Gloster LJ confirmed at [37] that, in order to amount to an agreement as envisaged by section 69 of the Act, ‘sufficiently clear wording is necessary, albeit that no express reference to section 69 is required’.
In the present case, the Court found that there was in fact no general or wholesale incorporation of the ICC Rules 1998 into the Agreement since paragraph 2 of Annex 2 of the Agreement only provided for the incorporation of the ICC Rules 1998 only in the case of disagreement or gap in the procedural rules of arbitration otherwise agreed by the parties. Further, Article 28.6 of the ICC Rules 1998, which Crescent sought to argue was incorporated into the Agreement, dealt with the right to appeal (i.e. post-award), whilst Annex 2 of the Agreement was concerned with the procedures of the arbitration itself, and not the procedure post-award.
In the circumstances, the Court found that parties are to be regarded as having preserved their right of appeal under section 69 of the Act. The Court then turned to decide on NIOC’s application for permission to appeal the Partial Award.
In considering the application for permission to appeal, the Court found that the requirements as set out at Section 69(3)(b) and 69(3)(c)(i) of the Act were not met and refused to grant NIOC permission to appeal against the Partial Award.
NIOC argued that the Tribunal had applied the incorrect legal test when it determined that NIOC was precluded from raising the issue of sanctions in the damages phase, and therefore the Partial Award was ‘obviously wrong’. NIOC argued, inter alia, that:
the Tribunal should have considered whether the points raised by NIOC at the remedies stage ‘should’ have been raised sooner, such that it was abusive for them to have been raised at a later stage;
because the arbitration was bifurcated from an early stage, the points raised by NIOC were appropriately raised in relation to quantum rather than in relation to liability; and
the Tribunal failed to recognise the distinction between the effect of sanctions on NIOC (which was not open to NIOC to raise at the remedies phase as it would be something which went to liability, not quantum) and the effect of sanctions on Crescent, specifically whether Crescent could not have performed its obligations to NIOC (something that went to quantum, not liability).
Conversely, Crescent disagreed, and also argued as a preliminary matter that the Tribunal was not asked to determine the legal question which NIOC had raised in their permission to appeal application. In this regard, Crescent argued that the parties had relied upon the same legal test (i.e. whether NIOC was precluded from raising certain points at the quantum tranche of the arbitration depended on whether it ‘could and should’ have raised them at the earlier liability stage of the proceedings). On that basis, Section 69(3)(b) of the Act (i.e. whether the Tribunal was asked to determine the legal question that was the subject matter of the leave application) was not satisfied.
In relation to Section 69(3)(b) of the Act, the Court decided that Crescent’s objection was not satisfied because:
the purpose of the requirement in Section 69(3)(b) of the Act was to prevent parties from raising wholly new points which were not in play before the arbitrators, and need not actually be articulated as a question of law; and
whilst the question of law which NIOC sought permission to appeal was not one which the arbitrators were asked to determine, this was only because it was common ground between the parties. Nonetheless, it was still integral to the resolution of the dispute.
In relation to Section 69(3)(c)(i) of the Act (i.e. whether the decision of the Tribunal was obviously wrong), the Court held that NIOC had not shown ‘anything wrong’ much less anything ’obviously wrong’) with the Tribunal’s decision regarding the application of the correct legal test when determining the res judicata/abuse of process issues.
First, whilst the Tribunal did not refer to the specific legal test and had adopted ‘somewhat loose language’ in expressing their conclusions, the Court found that these were not critical, and it was clear that the Tribunal had applied the correct legal test.
Second, the fact that the arbitration was bifurcated was not a point of any real significance because, if NIOC had argued at a single (liability and quantum) trial that sanctions meant that Crescent was not entitled to the damages sought, that would run entirely counter to any finding of liability against NIOC which did not also take account of those sanctions.
The English court explained that the Tribunal’s findings were ‘something really quite straightforward’ — insofar as NIOC had not advanced a defence based on sanctions to excuse its non-performance of the Agreement, NIOC should not be permitted to put forward a case which required the Tribunal to take sanctions into account as a reason why Crescent ought to be precluded from its damages sought. The learned judge considered that requiring the Tribunal otherwise would have forced them into engaging in an exercise which ‘would have been quite unreal, in that it would have required the Tribunal to suppose that, despite being liable to Crescent notwithstanding the sanctions, NIOC was not obliged to pay the damages sought by Crescent precisely because of those self-same sanctions’ (emphasis in italics in original).
Finally, the Tribunal had clearly considered and were clearly entitled to consider that, since NIOC could have raised the issue of sanctions at the liability stage, to seek to do so (albeit in relation to Crescent than itself) at the remedies phase amounted to an abuse of process.
The English court noted that having a bifurcated trial should not permit a party to advance cases ‘which, if not strictly inconsistent, are nonetheless cases which place the tribunal (whether arbitrators, as in the present case, or a court) in an [unreal] position [as described above]’.
In the premises, the Court refused NIOC’s application for permission to appeal under Section 69 of the Act.
This article is produced by our Singapore office, Bird & Bird ATMD LLP and was first published on LexisNexis. It does not constitute as legal advice and is intended to provide general information only. Information in this article is accurate as of 28 July 2022.