I often tell my clients that sometimes, like an arrow, we need to pull backwards in order to launch forward and hit our target. If you’ve been following the UK energy market recently, you’ll know the atmosphere can feel a bit like a tense archery tournament. We are in the midst of the most significant shake-up to our electricity network in decades. The National Energy System Operator (NESO), alongside Ofgem and government partners, has effectively pulled the string back on a grid queue that had bloated to over 700 GW, four times what we actually need by 2030.
The recent Gate 2 to Whole Queue ('G2TWQ') notifications, which landed in December 2025, represent the "release" of that tension. But as the dust settles, developers, investors, and lenders are finding that the "target" has moved. We are no longer in a world of "first-come, first-served"; we are now in a world of readiness and strategic alignment.
I’m seeing a consistent set of anxieties from clients: it isn’t just about the date on the letter, it’s about how that date ripples through Share Purchase Agreements (SPAs), Facility Agreements, and the internal promises made to Investment Committees.
The reform has bifurcated the project pipeline into two distinct realities. If your project received Gate 2 status, it has been deemed "ready" (meaning you have the land rights) and "strategically aligned" with the Clean Power 2030 (CP30) Action Plan. You are now in the "new project pipeline."
To put this in context, the scale of this reordering is significant. This isn't a minor reshuffle: it's a fundamental reordering of the UK's renewable pipeline.
If you received a Gate 1 notification, the system has determined your project is "not yet ready or needed." You aren’t necessarily out of the game forever, but can expect an Agreement to Vary (ATV). This legal document suspends your existing obligations and turns your previous connection date into a mere "indicative" placeholder until you can successfully reapply in a future window, likely not before April 2026.
For those of you in the middle of M&A transactions, these notifications are deal-shapers. In a typical renewable energy SPA, "Conditions Precedent" (CPs) often revolve around securing a "firm" grid connection offer.
The current reform introduces a period of profound ambiguity. While you may have a Gate 2 notification, the formal Modification Offer, the document that actually contains your confirmed connection date, works, and costs, might not arrive until Q2 or even Q3 of 2026.
This creates a "valuation gap." If a project was marketed on the basis of a 2027 energisation but receives a "Phase 2" outcome (meaning a firm connection from 2031 onwards), the financial model breaks. We are currently redrafting completion metrics to account for this. Instead of binary "Grid Offer" triggers, we're now drafting SPAs with:
If developers are anxious, lenders are too. Facility Agreements have been drafted assuming grid certainty that the reform has temporarily suspended.
If you are expecting a non-firm connection date in 2026/2027 but won’t see your full offer until late 2026, your debt drawdown schedule could be at risk. Lenders are now asking for sight of the full Modification Offer before entering deep discussions, which can stall a project for months.
Furthermore, the reform introduces the Progression Commitment Fee (PCF). This is a new, ratcheted security starting at £2,500/MW and potentially rising to £10,000/MW. If your project terminates or reduces capacity at the first milestone (M1), this fee becomes payable. From a legal drafting perspective, we must ensure that these potential liabilities are correctly allocated between the borrower and the sponsor, and that internal Investment Committees are aware that "security" now involves more than just the traditional TO spend guarantees.
We're advising clients to include PCF liability caps in their development budgets now. For a 100 MW project, that's potentially £1 million at risk if you miss M1. This needs to be flagged to Investment Committees as a new category of development risk, separate from traditional cost overrun provisions.
One of the most immediate impacts of receiving your offer will be the end of the securities freeze. Since January 2025, NESO has held back on new security requirements to provide certainty during the transition. Once you sign your Gate 2 Modification Offer, you have just 30 days to place the necessary securities.
For many developers, the jump from "indicative" security to "actual" security could be significant, ranging from thousands to several million pounds depending on Transmission Owner (TO) spend. You need to be "liquid" and ready to move. If you miss that 30-day window, your project’s progress could be jeopardised.
We recommend clients review the relevant liquidity position now. If you're part of a portfolio transaction, ensure parent company guarantees or letters of credit can be issued within the 30-day window. The risk is that deals collapse when buyers discover they can’t mobilise securities in time.
If you are developing a co-located (hybrid) project, the news is nuanced. NESO treats each technology as a separate asset. We’ve seen cases where the battery element gets Gate 2 status while the generation element (like solar) is relegated to Gate 1.
There's also a critical nuance regarding import/export capability. If your Battery Energy Storage Systems (BESS) was registered as "export-only" during queue formation (a common error in early applications), you may receive a Gate 2 offer that technically succeeds but doesn't permit grid charging. This isn't just an administrative issue, it fundamentally undermines your revenue model. Check your connection application documents now.
For Battery Energy Storage Systems (BESS) more broadly, the market is facing a "saturation risk." More BESS projects were protected (roughly 62 GW above requirements) than the Clean Power Action Plan strictly needs. The market is entering a 'race to energisation' phase. It's no longer enough to have an offer, you need to be first to commission. This shifts the competitive advantage from financial firepower to execution capability: EPC contractor relationships, supply chain security, and planning consent speed now matter more than ever.
If you are unhappy with your Gate 1 status, you have options, but they are narrow. You can submit a query via the Connections Portal, and NESO aims for a "clear update" within two working days.
Let's be clear: successful challenges will be rare. NESO's methodology has Ofgem approval, and the threshold for overturning a determination is high. You would need to demonstrate a clear error in data or process, not merely argue that you disagree with the outcome. That said, if you genuinely believe there's been a mistake (for example, your land rights evidence wasn't properly considered), it's worth querying within the tight timelines available.
However, be warned: the pipeline is considered final. No new projects can be added or reordered. Unless you can prove an error in the data used—rather than just a disagreement with the methodology—a challenge is unlikely to move you from Gate 1 to Gate 2 in this window. The legal threshold for "determination" by Ofgem is whether the network company failed to follow the approved process, not whether the outcome was "fair" in a general sense.
Finally, clients have made commitments to their internal Investment Committees based on a "first-come, first-served" logic that no longer exists.
You need to communicate that the milestone obligations (M1, M2, etc.) are now being enforced with a much "tougher line" than before. Missing a planning submission date (M1) or failing to obtain consent (M2) can now lead to the termination of your offer. This isn't just a grid issue; it’s a compliance and risk management issue that needs to be reported up the chain immediately.
Board Communication Checklist:
We're seeing boards and investment committees grappling with how to report this shift. The old narrative of 'we secured a 2027 connection date in the queue' is defunct. The new narrative needs to be: 'we have Gate 2 protection, we're in Phase [1/2], and our critical path to energisation is [X months], subject to receiving the formal Modification Offer by [Q2/Q3 2026].'
We are in a period of profound recalibration, but the strategic direction is clear: a faster, cleaner, more deliverable pipeline. The 'zombie projects' that clogged the queue for years are being cleared. For those with Gate 2 status, the road ahead is opening up, but only if you act decisively.
My three immediate action points:
The grid reform has pulled us back, but it's created the space to launch forward more powerfully than before. The projects that move first, and smartest, will be the ones powering Britain's clean energy future.
If you would like to discuss how the grid reform affects your projects or have questions about any of the issues raised in this article, please do not hesitate to get in touch.